| Equipment | Condition | Work done | Next due |
|---|---|---|---|
| MSB-1Main switchboard, 2000 A | 2 | IR scan, visual | May 2027 |
| TX-2Dry-type transformer, 112.5 kVA | 1 | IR scan, visual | Nov 2027 |
| PP-4APanelboard, 225 A | 3 | IR scan | Repair Dec 2 |
| ATS-1Automatic transfer switch, 400 A | 2 | Visual | Feb 2027 |
Finding, PP-4A
Breaker 14, phase C terminal running 22 °C above similar connections under normal load. Client notified on site. Repair and re-scan scheduled for Dec 2.